Provost Driver Court
Project Overview
We have completed our sewer repair and ground stabilisation works near to Provost Driver Court in Renfrew.
The project was delivered by our contractor George Leslie Ltd.
At a Glance
- Sewer Repair
- Ground Stabilisation Works
- Main Contractors George Leslie Ltd.
Mammoth Operation
Significant groundwork was undertaken to prepare for the new sewer being installed
What We Are Doing
Scottish Water and its main contractor George Leslie have replaced around 30m of waste water pipe and surface water pipe beneath King George V Playing Fields, adjacent to Provost Driver Court Sewage Pumping Station.
Two manholes have also been constructed.
These were complex works due to the poor, sandy ground conditions and high water table within the work area. Specialist sub-contractors and equipment were deployed.
Why We Are Doing It
In 2020 we identified ingress of silt to the waste water infrastructure within Provost Driver Court Sewage Pumping Station. Steps were taken to rectify the situation, however, the silt reappeared within a matter of weeks.
Investigations were carried out and a sunken area of land was identified on the playing fields above the main sewer line running into the pumping station. A damaged section of waste water pipe was allowing sand and silt to enter the waste water network.
These works will help return the existing pumping station to full operation, removing the need for continued Scottish Water site presence and increased maintenance visits carried out by Scottish Water and a wide range of contractors.

A sunken area of land was identified

CCTV investigations revealed damage to a section of waste water pipe

Deliveries
Sheet piling being delivered ahead of the main construction works.
Information Event
These are the posters shown at the information event held before work began
View documents