Kirkintilloch Water Main Upgrade

Project Overview
Scottish Water has completed work to upgrade the water pipes in Kirkintilloch to support community growth and ensure its customers continue to enjoy fresh, clear drinking water for years to come.
The work took place on both Freeland Place and a section of Forth and Clyde Canal Towpath.
Scottish Water Horizons delivered the work in conjunction with Mackenzie Construction.
At A Glance
- Water main upgrade to support community growth
- From Monday, 11 August 2025
- Freeland Place and Forth and Clyde Canal towpath
- Traffic management measures expected
- Delivered by Scottish Water Horizons and Morrison Construction
Latest Update - January 2026
The canal path was fully reinstated and reopened on 19th December. The site cabin and equipment were also removed at this time. All planned work at this location has now been successfully completed.