project statys delivery

Project Overview

Scottish Water is investing approximately £3.56 million to upgrade approximately 2.5km of mains water pipes in Oban.

The project is expected to last 14 months and aims to ensure customers continue to enjoy fresh, clear drinking water and reduce the chances of pipes bursting.  

Caledonia Water Alliance and their contractor, AS Utilities, will be carrying out this work on our behalf.

The project will run across multiple sections.

At a Glance

  • £3.56m investment
  • 2.5km mains upgraded
  • 14-month project
  • Carried out by our alliance partner Caledonia Water Alliance

What we are doing

We are upgrading approximately 2.5km of mains water pipes in an area where customers have experienced around 10 bursts and interruption to supplies since 2020. 

Over 14 months, there will be multiple sections which stretch from an area at Oban Saints Football Club to Polvinster Road.

As part of the work, we will need to widen Glencruitten Road and break a large quantity of rockface/rock near Polvinster Road. There may be some noise from rock breaking work but we will do our best to keep all disruption to a minimum.

The phases are outlined below. Please note that all dates are subject to change as there is a large amount of rock expected, which may affect the overall timing of the programme.  

 

Section 1 - complete

Starting mid-April for approximately four weeks pipelaying will commence around Oban Saints Football Club - the car park will remain closed during this period, the pitch will remain open.

Section 2

A new water main will be installed on Mossfield Avenue from Wednesday, 28 May 2025, and will be done in three phases over approximately nine weeks (full details below).

Section 3

Glencruitten Road will be widened and traffic management will be in place. Timescales to be confirmed.

Section 4

Polvinster Road will be closed between 9.30am and 3pm for this section. Timescales to be confirmed.

Latest Information - Mossfield Avenue (Section 2)

The next section of these essential works involves the installation of a new water main in Mossfield Avenue. This work will be split into three phases, which are outlined below.

The work will start from Wednesday, 28 May 2025 and last approximately nine weeks (three weeks for each phase).  

Phase 1 - Mossfield Avenue (Football pitch car park to Glencruitten Drive):

  • From Wednesday, 28 May, this part of Mossfield Avenue will be closed to vehicles for approximately three weeks, with no parking allowed and no vehicle access to the football pitch car park.

Phase 2 - Mossfield Avenue (Glencruitten Drive to Mossfield Drive):

  • Following Phase 1 and for approximately three weeks, four-way traffic lights will be in place while we work across the junction at Mossfield Avenue and Glencruitten Drive.
  • There will be a lane closure on Mossfield Avenue with no on-street parking, and a one-way southbound system will be in operation.

Phase 3 - Mossfield Avenue (Mossfield Drive to Car Park Entrance):

  • Following Phase 2, there will be a lane closure on Mossfield Avenue with no on-street parking, and a one-way southbound system will be in operation. This will last approximately three weeks. 
Satellite image of roadworks planned to help accommodate a water main upgrade in Oban

Upcoming Section of Work - Mossfield Avenue

Work to commence from Wednesday, 28 May 2025 for approximately nine weeks